Operators attempting to insert one control rod accidentally withdrew three causing a 15-minute uncontrolled sustained reaction at the number 1 reactor of Shika Nuclear Power Plant.[4]
During preparation of a uranyl nitrate solution, uranium in solution exceeded the critical mass, at a uranium reprocessing facility in Tokai-mura northeast of Tokyo, Japan. Three workers were exposed to (neutron) radiation doses in excess of allowable limits. Two of these workers died. 116 other workers received lesser doses of 1 mSv or greater though not in excess of the allowable limit.[5][6][7][8]
After the 2011 Tōhoku earthquake and tsunami of 11 March, the cooling systems for three reactors (numbers 1, 2 and 4) of the Fukushima II (Fukushima Dai-ni) nuclear power plant were compromised due to damage from the tsunami.[9] Nuclear Engineering International reported that all four units were successfully automatically shut down, but emergency diesel generators at the site were out of order.[10] People were evacuated around 10 kilometres (6.2 mi) from the plant, due to possible radioactive contamination.[11][12] By 15 March, all four reactors at Daini were reported shutdown, cold and safe.[13]
After the 2011 Tōhoku earthquake and tsunami of 11 March, the cooling systems for multiple reactors (units 1, 2, 3) and spent fuel cooling ponds (all 6 units and central pool) of the Fukushima I (Fukushima Dai-ichi) nuclear power plant were compromised due to damage from the tsunami.
List of plants affected by 2011 Tōhoku earthquake and tsunami