The metra potential method (MPM) (Méthode des potentiels Métra) is a method used in project management which was developed by French researcher Bernard Roy in 1958 for the construction of the French paquebot and of the first French nuclear power plant.[1]
MPM is a means of describing organizing and planning a project. It is an equivalent of the PERT method.
Using summits for tasks and path for interdependencies between the different tasks, the solution is set are graphically.
Using MPM, the length of the critical path is shown directly in the diagram and the critical path itself can be identified easily.
References
Content Disclaimer
Informasi ini disarikan dari Wikipedia dan disajikan kembali untuk tujuan edukasi. Konten tersedia di bawah lisensi CC BY-SA 3.0. Kami tidak bertanggung jawab atas ketidakakuratan data yang bersumber dari kontribusi publik tersebut.
- The information displayed on this website is sourced in part or in whole from Wikipedia and has been adapted for the purpose of restating it. We strive to provide accurate and relevant information, however:
- There is no guarantee of absolute accuracy. Wikipedia is an open, collaborative project that can be edited by anyone, so information is subject to change.
- It is not intended to constitute professional advice. The content displayed is for informational and educational purposes only. For important decisions (e.g., medical, legal, or financial), please consult a professional.
- Content copyright. Wikipedia is licensed under the Creative Commons Attribution-ShareAlike License (CC BY-SA). This means that content may be reused with appropriate attribution and shared under a similar license.
- Responsible use. Any risk arising from the use of information from this website is entirely the responsibility of the user.