Hydropower station in China
Dam in at the junction of Mangkam and Batang
Suwalong Hydropower Station苏洼龙水电站 Country China Location at the junction of Mangkam and Batang Purpose Power, flood control, navigation Opening date 2022 Construction cost ¥ 17.89 billion
The Suwalong Hydropower Station (Chinese : 苏洼龙水电站 ),[ 1] is the hydropower project
that is located in the upper reaches of the Jinsha River at the junction of Mangkam County in Tibet and Batang County in Sichuan .[ 2] It is the first installed million-kilowatt-level hydropower station in Tibet.[ 3]
With a total investment of ¥ 17.89 billion,[ 4] the plant's total installed capacity is 1.2 million kilowatts , [ 5] which is more than double that of the Zangmu Dam .[ 6] Once completed, the project would generate 2,000 MW of power.[ 7]
History
In November, 2015, the National Development and Reform Commission officially approved the construct of Suwalong Hydropower Station.[ 8]
On November 21, 2017, Suwalong Hydropower Station dammed the river.[ 9]
The plant became fully operational in November 2022.[ 10]