The project was developed by Recurrent Energy, which was acquired by the Sharp Corporation in late 2010.[3] Recurrent Energy was subsequently acquired by the Chinese photovoltaic panel manufacturer Canadian Solar in February 2015.[4] Construction on the project was financed for about $275 million[5] and began in November 2015. The engineering, procurement, and construction contractor was McCarthy Building Companies and the project employed about 480 workers at its peak.[1]
The project uses approximately 700,000 CS6X-P series panels (polycrystalline, ~300 Wp each)[6] from Canadian Solar that are mounted on single-axis trackers.[1] It began sending electricity to the grid in late November 2016.[7] On November 30, 2016, Recurrent Energy sold a controlling interest in the completed facility to Southern Power. The electricity is being sold to Austin Energy under a 20-year power purchase agreement.[5]